Report on
Mold Outbreak
PLNU
Ryan Learning Center, Summer/Fall, 2003
I. Timeline
A.
Summer, 2002
·
Small mold outbreak in Reference
area. Treated by cleaning affected
books, and inquiring about air-conditioning system status.
B.
End of July, 2003
- We
noticed an outbreak in the 800’s-900’s in the reference area. Began contacting Physical Plant about
trying to deal with air conditioning system. We had hoped to treat the books ourselves. However, since the humidity in the room
was consistently 83%, it would have been useless to clean the books at
that time.
C.
August, 2003
- The
mold continued to grow and spread, and we continued to try to get someone
from our Physical Plant to realize the severity of the situation.
- Mold
had spread throughout reference area, and employees and students began
experiencing sneezing, breathing issues, etc. Nothing major, but we knew it was
there.
- We
contacted Julie Page, who advised us on how to clean the books ourselves,
and we proceeded with purchasing supplies to do so.
- Classes
began Mon., Aug. 25, and on Tues., Aug. 26, our Physical Plant manager
came through with outside experts, who said we had to close down the
whole library immediately (starting the next day). We had that day to move out of our
offices, and into the “old” part of the library.
- R
& M Mold Remediation specialists were contracted by our Physical
Plant to handle the whole process.
They sealed off the building, packed and removed the books
(6,000+) to their warehouse in Lakeside, and cleaned the affected areas thoroughly.
- There
was also an outbreak in our Media Collections Room in the LP
collection. That area was sealed
off as well, although it was not a public area, so it did not entail a
major disruption to the campus.
The LP’s were removed for cleaning.
- Library
reopened a week later but reference area was closed for two more weeks.
D.
September, 2003
- We
were able to move back into our offices and the reference area in
mid-September. However, the books
were still off-site being cleaned.
E.
September-November, 2003
- Books
were being cleaned off-site.
F.
December, 2003
- Books
were returned and reshelved. A few
(less than 100) of the books had to have the spines cut to get to the
mold, and they are still not available.
We have them back, but have to decide whether to rebind them or
not.
G.
January, 2004
- Media
collections room is still being worked on. The area will now be inaccessible for a
period of time in preparation for return of LP’s.
II.
Contributing Factors
A. Inadequate
air conditioning system
·
This has been a problem since RLC was built. The system has never pulled the humidity out
of the air adequately. In fact, humidity
in the old Ryan Library building (which has no air conditioning) is far lower
than the Reference area in RLC.
B. Chiller
·
The “chiller” was down for several days in
mid-August, which happened to be a time of high temperature/humidity in San
Diego.
C. Construction
of the new Bresee Lab
·
For quite a few
days the glass, having been removed for access from both the outside and the
inner wall that leads to the Reference area, allowed the outside air to
infringe upon the environment in the Reference area, which resulted in higher
temperature and relative humidity.
Although the outside wall now is done, the inner wall is still not complete.
III. Cleaning Process
·
According to R&M, the books were cleaned with an
alcohol solution, vacuumed, and “air blasted.”
IV. Lessons Learned
·
Communication is vital through whole process.
·
If an outside contractor is used, find out exactly
what the plan is, how it will be implemented, and when the process will
end. (In our case, this was really more
of a communication issue with our Physical Plant than with R&M.)
·
Nothing happens quickly.
.