Report on Mold Outbreak

PLNU Ryan Learning Center, Summer/Fall, 2003

 

 

I.          Timeline

 

A.      Summer, 2002

 

·         Small mold outbreak in Reference area.   Treated by cleaning affected books, and inquiring about air-conditioning system status.

 

B.     End of July, 2003

 

 

C.     August, 2003

 

 

D.     September, 2003

 

 

E.     September-November, 2003

 

 

F.      December, 2003

 

 

G.    January, 2004

 

 

II.         Contributing Factors

 

A.   Inadequate air conditioning system

 

·         This has been a problem since RLC was built.  The system has never pulled the humidity out of the air adequately.  In fact, humidity in the old Ryan Library building (which has no air conditioning) is far lower than the Reference area in RLC.  

 

B.  Chiller

 

·         The “chiller” was down for several days in mid-August, which happened to be a time of high temperature/humidity in San Diego.

 

C.  Construction of the new Bresee Lab

 

·         For quite a few days the glass, having been removed for access from both the outside and the inner wall that leads to the Reference area, allowed the outside air to infringe upon the environment in the Reference area, which resulted in higher temperature and relative humidity.  Although the outside wall now is done, the inner wall is still not complete.

 

III.        Cleaning Process

 

·         According to R&M, the books were cleaned with an alcohol solution, vacuumed, and “air blasted.” 

 

IV.        Lessons Learned

 

·         Communication is vital through whole process. 

·         If an outside contractor is used, find out exactly what the plan is, how it will be implemented, and when the process will end.  (In our case, this was really more of a communication issue with our Physical Plant than with R&M.)

·         Nothing happens quickly.

 

 

.