Timeline for remainder of 1998/99
per Earl and Roberta's email re: Notes from IPG Meeting on 10/19/98
-
Obtain detailed information about Internet station conversions by Nov.
1998
-
Complete Phase 1 (aal, mus, fvl, cjk) installations in Nov. - Dec. 1998
-
Complete technical work on CD interface by Dec. 1998
-
Perform major upgrade of all station configurations by end of Dec. 1998
-
Finalize list of hardware (RAM and ?) upgrades and software (NT Workstation)
needed for machines (CD ROM & Internet) to be converted.
-
Order hardware and software for conversions.
-
Convert CD NET stations in Jan. - Mar. 1999
-
Convert Internet stations in Jan. - Jun. 1999
-
Order Phase 2 Infostations (sshl 17, mus/fvl, cmrr-their $) in Feb. 1999
-
Install Phase 2 Infostations at quarter break in Apr. 1999
-
Determine remaining budget and order Phase 3 Infostations by Jun. 1999
-
Install Phase 3 Infostations in summer 1999